Concrete Mix Ratios

How much cement do I need for 1 tonne of ballast?

One tonne of ballast typically needs about 6 to 8 bags of 25 kg cement at common 1:5 to 1:6 ratios. See how to convert volume ratios into weights.

On this page
  1. Short answer
  2. Why weight and volume confuse people
  3. The calculation
  4. Quick table
  5. Smaller bags of ballast
  6. Builders mix per cubic metre
  7. Tips

Short answer

For commonly used ratios of 1 part cement to 5 or 6 parts ballast by volume, one tonne of ballast needs roughly 150 to 190 kg of cement. That is about 6 to 8 bags of 25 kg cement. Treat this as an estimate, because the weight of ballast per cubic metre varies.

Why weight and volume confuse people

Mix ratios, such as 1 : 5, are by volume: one bucket of cement to five buckets of ballast. Ballast, however, is sold by weight (tonnes or bulk bags). To get from one to the other, you need to know roughly how heavy a cubic metre of loose ballast is.

The calculation

  1. Ballast volume: loose, dry ballast weighs very approximately 1.5 to 1.7 tonnes per cubic metre, which means 1 tonne is about 0.6 to 0.65 m³. Damp ballast and different blends vary.
  2. Cement volume: at 1 : 6, cement is one-sixth of the ballast volume, so about 0.1 m³. At 1 : 5, it is one-fifth, about 0.12 to 0.13 m³.
  3. Cement weight: cement has a bulk density of around 1,440 kg/m³ (about 1.44 tonnes per m³), so 0.1 m³ is about 145 kg, and 0.125 m³ is about 180 kg.
  4. Bags: divide by 25 kg to get about 6 to 7 bags.

Quick table

Ratio (cement : ballast) Cement per tonne of ballast (approx.) 25 kg bags (approx.)
1 : 6 about 145 to 155 kg 6
1 : 5 about 175 to 190 kg 7 to 8

The yield from one tonne of ballast with those cement quantities is very roughly half a cubic metre of finished concrete, give or take. If you need an exact volume of concrete, see how to calculate how much concrete you need.

Smaller bags of ballast

If you buy ballast in 25 kg bags, the same estimate applies: loose cement and loose ballast have similar bulk densities, so by weight the mix comes out at roughly one bag of cement for every five to six bags of ballast. That is only an approximation, since both materials vary, so where possible measure with a bucket or tub for consistency. If a bag of ballast states a recommended mix on the label, follow it.

Builders mix per cubic metre

In New Zealand and Australia, builders mix is the equivalent of ballast. Estimating cement for a cubic metre follows the same approach: a cubic metre of finished concrete needs roughly 1.5 m³ of dry materials, of which about one-sixth to one-seventh is cement. See how much cement is needed for 1 cubic metre of concrete.

Tips

  • Always use the same measuring container for cement and ballast.
  • Keep the ballast roughly as damp as it arrives, and add water gradually; see how much water to add to concrete.
  • Where strength matters, such as structural work, use a specified mix and not a bucket ratio. For background on ratio choices, see our concrete mix ratios guide.

The complete guide to concrete mix ratios

Concrete Mix Ratios: Cement, Sand, Ballast and Water Explained
Read the guide

Keep exploring

Guides from other topics

All topics →