The basic formula
Concrete is ordered and measured by volume. For any rectangular shape, the formula is:
Volume = length × width × thickness (or height)
All three measurements must be in the same unit. The result is in cubic metres (m³) if you work in metres, or cubic feet if you work in feet, which you convert to cubic yards by dividing by 27.
Step-by-step
Metric
- Measure length, width and thickness in metres (convert millimetres by dividing by 1,000, so 100 mm is 0.1 m).
- Multiply them together to get cubic metres.
- Add an allowance for waste (see below).
Imperial
- Measure length and width in feet, and convert the thickness from inches to feet by dividing by 12 (so 4 in is 0.333 ft).
- Multiply to get cubic feet.
- Divide by 27 to get cubic yards.
- Add an allowance for waste.
Shapes
- Rectangular slab, footing or wall: length × width × thickness.
- Round column or post hole: π × radius² × depth, with radius being half the diameter.
- Triangular section (such as the wedge of a step): ½ × base × height × width.
- Irregular areas: break them into rectangles, circles and triangles, calculate each one and add the volumes together.
For fence posts, the hole volume minus the volume of the post gives the concrete needed. A worked example is in concrete mixes for footings, foundations and fence posts. For steps and staircases, see mix ratios for roof slabs, columns, lintels and steps.
Worked example: a 24 × 24 ft slab, 4 in thick
- Thickness: 4 in ÷ 12 = 0.333 ft
- Volume: 24 × 24 × 0.333 ≈ 192 cubic feet
- In cubic yards: 192 ÷ 27 ≈ 7.1 yd³
- With 10% extra: about 7.8 yd³
Many thicknesses and ready-mix minimums apply, so a supplier may suggest 8 yd³. The same slab in metric (7.3 × 7.3 m × 0.1 m) would be about 5.3 m³ before waste.
Bags needed
Bagged concrete mix is sold by weight, with a stated yield per bag. Typical yields are:
- 80 lb bag: about 0.6 cubic feet
- 60 lb bag: about 0.45 cubic feet
- 40 lb bag: about 0.3 cubic feet
That works out to roughly 45 bags of 80 lb, 60 bags of 60 lb or 90 bags of 40 lb for one cubic yard. Yields vary between brands, so check the bag. In metric, a 20 or 25 kg bag of mix typically yields in the region of 0.01 m³, so a cubic metre needs about 80 to 100 bags, which is why larger jobs usually go to ready-mix or site-mixed batches.
If you are mixing from cement, sand and aggregate rather than from a bagged mix, you need roughly 1.5 times the finished volume in dry materials, divided by your mix ratio. See how much cement is needed for 1 cubic metre of concrete and how much cement you need for 1 tonne of ballast.
Waste allowance
Add around 5 to 10% to cover spillage, uneven ground, slight over-excavation and formwork that bows out under load. Ordering a little too much is cheaper than running short in the middle of a pour, since a cold joint can weaken the slab.
Ready-mix versus bags
For small jobs, such as a few fence posts or a small pad, bags are convenient. For larger pours, ready-mix delivery avoids hours of mixing, though suppliers may have minimum loads or short-load charges. For the cost comparison, see whether it is cheaper to mix your own concrete or buy bags. If you plan to hand mix, see how to mix concrete by hand without a mixer to judge whether the volume is realistic.
Common mistakes
- Mixing units (for example, feet for length and inches for thickness).
- Forgetting to account for the depth of base material that is not concrete (see how much gravel you need under a concrete slab).
- Using nominal instead of actual dimensions for the formwork.
- Not allowing for waste.
For help choosing proportions once you know the volume, see our guide to concrete mix ratios.