Short answer
A concrete path for foot traffic is commonly about 75–100 mm (3–4 in) thick, laid over a compacted sub-base. Many DIY guides settle on 100 mm as a sensible standard, since it gives a little margin for wheelbarrows and uneven ground. If vehicles will ever drive over it, treat it as a driveway and make it thicker; see below.
Thickness by use
| Use | Typical concrete thickness |
|---|---|
| Light garden path, foot traffic only | about 75–100 mm (3–4 in) |
| Path used with wheelbarrows, bins, mobility scooters | about 100 mm (4 in) |
| Occasional light vehicle crossing | about 100–150 mm (4–6 in), often with mesh |
| Driveway | commonly 100–150 mm (4–6 in), more for heavy vehicles |
These are general figures. Soft ground, frost-prone areas and heavier loads all call for more thickness or a stronger base.
Sub-base
The concrete needs something solid under it. A layer of compacted crushed stone or hardcore (MOT Type 1 in the UK), commonly around 75–100 mm deep, is typical for paths. Strip topsoil first, and compact in layers. For details, see how much gravel you need under a concrete slab, and why you shouldn’t just pour over dirt.
Width, fall and edges
- Width: about 900 mm (3 ft) is a comfortable minimum for a main path; secondary paths can be narrower. Allow more for wheelchair access.
- Fall: build in a slight cross-fall, roughly 1:80 (about 12 mm per metre), so rainwater drains off the surface rather than ponding.
- Edges: forms of 75–100 mm timber pegged firmly keep the edges straight and the depth consistent.
- Next to buildings: keep the surface below the damp-proof course and slope it away from the wall.
Joints and reinforcement
Paths crack where the concrete shrinks, so joints give it somewhere to do so neatly. For a 100 mm path, a rule of thumb is joints at intervals of roughly 24–36 times the thickness, which means around 2.4–3.6 m; for narrow paths, joints about every 1.5–2 m are also common. Details are in control joint spacing in concrete slabs.
Many foot-traffic paths on firm ground are laid without steel, and some people add light mesh to hold cracks tight. See rebar or wire mesh in a concrete slab for a fuller discussion.
Mix and curing
A general-purpose mix, often around 1 : 2 : 4 (cement : sand : coarse aggregate) by volume or a bagged or ready-mix equivalent, is typical. More in concrete mixes for driveways, paths and pervious paving. Keep it damp or covered for several days afterwards, as described in curing concrete.
Quantity example
A path 10 m long, 1 m wide and 100 mm thick needs 10 × 1 × 0.1 = 1 m³ of concrete, plus a margin of roughly 5–10%. The sub-base at 100 mm deep needs a similar volume of stone before compaction allowance. Bagged concrete of this size means a lot of bags; compare with ordering ready-mix in is it cheaper to mix your own concrete.