A patio should slope gently away from the house so rainwater runs off rather than pooling or heading towards the walls. Commonly quoted figures are around 1 in 80 in the UK (about 12 mm of drop per metre), and about 1/8 to 1/4 inch per foot in the US (roughly 1 to 2 percent). Treat these as typical starting points, and follow any local building guidance or product instructions.
Typical fall figures
| Expression | Approximate drop |
|---|---|
| 1 in 80 | about 12 mm per metre |
| 1 in 60 | about 17 mm per metre |
| 1/8 inch per foot | about 10 mm per metre (about 1 percent) |
| 1/4 inch per foot | about 21 mm per metre (about 2 percent) |
Smooth surfaces such as porcelain, or very large paved areas, may need a little more fall than rough surfaces. Too much slope makes furniture wobble and can be noticeable underfoot.
Which direction
- Away from the house is the usual rule, so water does not run towards walls, doors or air bricks.
- Aim for a lawn, planted border, drain or soakaway where the water can go. Do not direct it onto a neighbour’s land.
- If the ground slopes towards the house, you may need a drain or channel along the house edge or a swale to take water away.
Setting and checking the fall
You can build the fall into the sub-base and the bedding layer, but it is best set in the base so the bedding stays an even thickness.
- Set string lines, with the end furthest from the house lower by the amount you calculate (for example, a 4 m patio at 1 in 80 drops about 50 mm).
- Compact the base to those lines. See how deep the sub-base should be for a patio.
- Bed the slabs or pavers to the string line. See mortar mix guide.
- Check with a spirit level and a spacer block. A spacer of the right thickness under one end of a level shows when you have the right fall. For a 1 in 80 fall, a 1.2 m level needs about a 15 mm spacer.
Where the water goes
- Run-off to lawn or beds is the simplest solution where the soil drains well.
- Channel or linear drains collect water at low edges or against the house.
- Soakaways take water into the ground, but need suitable soil and space, and are best planned carefully.
Fall and the damp-proof course
In the UK, paving next to the house is generally recommended to sit well below the damp-proof course, often quoted as at least 150 mm. Check this before setting levels. See laying paving slabs on an existing concrete base for how adding layers raises the finish.
Permeable surfaces and rules
Permeable paving and open-jointed surfaces allow water to soak through into the base, but they still benefit from a gentle fall and a free-draining base. Some areas have rules on hard surfaces. For example, in England, paving more than a certain area in a front garden with impermeable material may need planning permission unless it drains to a permeable area. Check current local rules before you start.
Mistakes
- A completely flat patio.
- Sloping towards the house.
- Fall built into a very thick or uneven bedding layer.
- Forgetting the surface height at doors and the DPC.
More on getting the build right is in common mistakes to avoid when laying pavers.