Bricklaying and Mortar

How to Lay the First Course of Bricks Level and Straight

Step-by-step guide to laying the first course of bricks: dry laying to set out, building the corners, using a line and level, and fixing an uneven base.

On this page
  1. Why the first course matters
  2. What you need
  3. Before you start
  4. Step 1: Set out and dry lay the bricks
  5. Step 2: Lay the corner bricks first
  6. Step 3: Set up a line
  7. Step 4: Fill in between the corners
  8. Step 5: Finish the joints
  9. Common mistakes
  10. After the first course

Why the first course matters

Every course above the first copies its mistakes. If the first course is out of level or out of line, you will be correcting for it all the way up the wall, using up the mortar joint thickness as you go. Spending extra time here saves effort later.

What you need

  • Brick trowel, pointing trowel and jointing tool
  • Mortar board or spot board
  • Spirit level (long, around 1 m, plus a short one)
  • Builder’s line, line pins or corner blocks
  • Tape measure and a pencil or chalk
  • Gauge rod, if you have one
  • Brick hammer and bolster (for cuts)
  • Mortar mixed to a workable consistency; see mortar consistency

Before you start

  • Check the base is ready. The footing should be firm and clean; see how soon you can lay bricks on new concrete.
  • Check the footing level. Use your level or a laser or water level along the footing to find the highest point. This determines your starting height.
  • Choose the mortar. For most garden walls, see mortar mix ratios.
  • Decide your bond. The common ones are covered in brick bond patterns. Stretcher bond is the simplest for a first project.

Step 1: Set out and dry lay the bricks

Mark the wall line on the footing with chalk or a pencil. Then lay the bricks out along the line without mortar, spacing them with about a 10 mm gap for each perpend (use a spare piece of timber or a plastic spacer). This shows you how many whole bricks you need and whether you end up with an awkward cut brick at the end.

If it doesn’t fit, you can adjust the perpend gaps a little (by a millimetre or two each) or plan a neat cut, rather than a thin sliver. Mark the positions of the bricks, piers and corners on the footing. See pier spacing for single skin walls if your wall has piers.

Step 2: Lay the corner bricks first

Starting at a corner or end, spread a bed of mortar on the footing, about 10 mm thick once the brick is pressed down (see how thick mortar joints should be). Make the bed a little thicker and furrow it lightly with the trowel point, so it compresses evenly.

Press the first brick into the bed, tapping it down with the trowel handle until it is level and at the right height. Check it level along its length and across its width, and check it is plumb (vertical on its face) using the short level. Then lay the corner brick at the other end in the same way.

If the footing is uneven, the thickness of the mortar bed will vary, so make sure no bed goes thinner than about the minimum you can fill with mortar. If it’s out by more than that, get the footing corrected first or build it up with a stronger, thicker bed in stages instead of cramming a single deep bed.

Step 3: Set up a line

Stretch a builder’s line between the two end bricks, pulled tight and positioned at the top edge of the course, a hair off the face of the bricks. Use line pins or corner blocks to hold it. The line shows you the course height and the straightness of the wall for each brick in between.

Step 4: Fill in between the corners

Working from one end, lay a mortar bed for a few bricks at a time, so the mortar doesn’t stiffen. For each brick:

  1. Butter the end of the brick with a little mortar to form the perpend. Alternatively, “butter” the end of the previous brick.
  2. Press it into the bed against the previous brick, aiming for a gap of around 10 mm.
  3. Tap it down to the line and check its level and alignment with the line (it should just clear it, not touch it).
  4. Scrape off the mortar squeezed out of the joint with the trowel and put it back on the board.

Use the long level every few bricks to check the whole course is level and straight. Tap bricks with the trowel handle to adjust, not with a hammer. Fill the last brick of the run (the closer) carefully, buttering both ends.

Step 5: Finish the joints

When the mortar is firm enough to hold a thumbprint, tool the joints to your chosen profile and brush off crumbs. Do not wait so long that the mortar goes hard. Protect the new work from rain and frost; see curing brickwork.

Common mistakes

  • Skipping the dry lay and ending up with a sliver brick at the end.
  • Using mortar that is too wet or too dry.
  • Not checking level and plumb on the first bricks.
  • Letting the line touch the bricks, which pushes it out of line.
  • Spreading too long a mortar bed so that it stiffens before the bricks go on.
  • Disturbing bricks after they have been set, which breaks the bond.

After the first course

Once the first course is complete and checked, build up the corners as “leads” a few courses at a time, using a gauge rod to keep the courses to height, and run the line between them. Keep checking level and plumb as you go. A properly laid first course makes everything after it easier.

For a wider overview of the footing beneath it, see how deep a footing should be for a brick wall.