Bricklaying and Mortar

Curing Brickwork: How Long and How to Do It

How long to cure a brick wall and how to do it: typical 7 to 10 day damp curing, hot and cold weather precautions, and when mortar reaches full strength.

On this page
  1. The short answer
  2. What “curing” means for mortar
  3. How long to cure brickwork
  4. How to cure a brick wall
  5. Weather matters
  6. When can you plaster, load or build higher?
  7. Frequently asked questions

The short answer

For cement-based mortar, a commonly quoted guideline is to keep brickwork damp and protected for around 7 to 10 days, and longer in hot, dry or windy weather. The mortar continues to gain strength for about 28 days, which is the age at which strength is usually specified.

Practice varies by region and by mortar type. In some countries, particularly in hotter climates, wetting the wall for a week or more is standard. In cooler, damp climates such as the UK, the main concern is usually protecting fresh work from heavy rain, frost and too-rapid drying rather than adding water. Online advice varies between 7 days and 15 days or more, so treat these numbers as rules of thumb.

What “curing” means for mortar

Mortar hardens through a chemical reaction between cement and water (hydration). If the joints dry out too quickly, the reaction stops before the mortar has gained its strength, which can lead to weak, powdery or cracked joints and a poor bond with the brick.

Curing means keeping enough moisture in the mortar, and the temperature within a reasonable range, while it gains strength. Fresh mortar is typically firm to the touch within hours, but that is not the same as being fully cured.

How long to cure brickwork

Stage Typical timing
Mortar firm enough to tool the joints Within about an hour or so, depending on weather and brick absorbency
Initial curing period (keep damp / protected) Around 7 to 10 days
Extended curing in hot, dry or windy weather Often 10 to 14 days
Mortar reaches design strength About 28 days

Lime-based mortars set and gain strength more slowly than cement mortars, so they need protection for longer.

How to cure a brick wall

  1. Dampen the bricks before laying, if they are very dry or absorbent, so they do not draw water out of the mortar. Do not soak them.
  2. Finish the joints at the right time, once the mortar is thumbprint firm. See how to judge mortar consistency for what a good mix looks like.
  3. Keep the wall lightly damp for the first several days by misting with a hose or spray, usually morning and evening in warm weather. Avoid heavy jets that wash cement out of the joints.
  4. Cover the wall with damp hessian or polythene sheeting to slow evaporation, in dry weather, or to shed rain, in wet weather. Keep covers off the fresh joints so they don’t stain or mark them.
  5. Avoid disturbing the work. Don’t knock, lean or load the new wall in the first days.

Weather matters

  • Hot or windy weather: mortar can dry before it cures. Work in shade where possible, mist more often and cover the wall.
  • Cold weather: mortar does not gain strength normally close to freezing, and freshly laid mortar that freezes can be damaged. Guidance commonly suggests avoiding laying brickwork when temperatures are at or near freezing, or protecting the wall thoroughly with insulated covers. Check the mortar manufacturer’s limits, which are often given on the bag.
  • Rain: heavy rain can wash cement out of fresh joints. Cover the top of the wall at the end of each day.

When can you plaster, load or build higher?

There is no single answer. Builders often lay several courses a day, as long as lower courses are firm enough not to squeeze out. For plastering, loading with beams or building heavy structures on a wall, wait longer. Typically this is at least several days, and longer for heavier loads or cold weather. For structural work, follow the engineer’s or manufacturer’s instructions.

If a wall is built on a fresh concrete base, see how soon you can lay bricks on new concrete.

Frequently asked questions

How long does it take for a brick wall to dry? The mortar can feel dry on the surface within a day or so, but the wall holds moisture for much longer, often weeks, depending on thickness, weather and ventilation. Drying and curing are different things.

What happens if water gets behind brick? Water that gets behind the facing brick can lead to damp, efflorescence (white salts), frost damage in cold weather and decay of ties or backing. Good detailing (cavity trays, weep holes, sound pointing) lets moisture drain out. If you suspect a problem, find the source before repairing; repointing a brick wall can help where joints have failed.

How many days of curing does a concrete slab need? This is a separate question from brickwork. Concrete is also commonly cured for around 7 days, though specific guidance depends on the mix and conditions. See curing concrete for methods and timing.

For mortar proportions and how they affect strength, see mortar mix ratios for bricks and blocks.

The complete guide to bricklaying and mortar

Mortar Mix Ratios for Bricks and Blocks
Read the guide

Keep exploring