Typical sand and cement screed ratios
Traditional screed is a mix of cement and sharp sand with no coarse stone, so it can be compacted and finished to a flat surface. The ratio most often quoted is about 1 part cement to 3 to 5 parts sharp sand by volume, with 1:4 a common middle ground. A richer mix such as 1:3 is stronger but can shrink more; a leaner mix such as 1:5 is cheaper but can be weaker and more prone to dusting at the surface.
Ratios vary by country, standard and application. If you have a specification, a manufacturer’s data sheet or a structural drawing, follow it.
For the same mix idea applied to walls, see rendering and plastering walls: mix ratios, application and curing. Wall mixes use finer sand and are not a substitute for a floor mix.
Sand and water
- Sand type: sharp (also called grit or concrete) sand is typical for floor screeds. Soft building sand is finer and normally used for render and bricklaying, and it tends to give a weaker screed.
- Water: screed is mixed damp, not wet. A common test is to squeeze a handful. It should hold together like a snowball without leaving water on your hand, and it should not crumble when you open your fist. Too much water weakens the screed, increases shrinkage and lengthens the drying time.
Plasticisers and washing-up liquid
You will sometimes see advice to add washing-up liquid to a mix. The idea is that it entrains tiny air bubbles and makes the mix easier to work with less water. It is widely used in the trade, but the effect is not controlled, and too much can weaken the screed. A proper screed or mortar plasticiser, used at the dosage on the label, is the more predictable choice.
Worked example: how much cement and sand?
The exact figures depend on your cement bag size and sand, so treat this as an estimate and add a margin for waste.
Say you want a 40 mm screed over 10 m².
- Wet volume: 10 m² × 0.04 m = 0.4 m³.
- Dry volume: dry materials compact when mixed with water, so a common allowance is roughly 1.3 times the finished volume. 0.4 × 1.3 ≈ 0.52 m³.
- Split by ratio: for 1:4 there are 5 parts in total. Cement is about 1/5 of the dry volume, around 0.10 m³, and sand is about 4/5, around 0.42 m³.
- Convert cement to weight: loose cement weighs about 1,400 kg per m³, so 0.10 m³ is about 145 to 150 kg. That is roughly six 25 kg bags or three 50 kg bags.
Order a little extra sand and cement, since edges, thresholds and uneven slabs use more than the flat-area sum suggests.
For tile flooring, the same method works for the bedding layer. Use the planned bed thickness in place of 40 mm. Thinner beds need much less material, but a base that is out of level needs more, which is why checking the slab first is useful.
Cement and tile cement are different
Ordinary Portland cement is an ingredient of the screed. “Tile cement” usually refers to a ready-made tile adhesive, which is a cement-based powder with polymers and fine sand that is used in a thin layer to stick tiles down. They are not interchangeable. Do not use a tile adhesive as a substitute for the screed itself.
Laying and curing tips
- Compact the screed firmly and level it off with a straight edge.
- Protect it from drying too fast. Cover it with plastic sheeting or keep it lightly damp for the first few days.
- Check the depth against what your floor needs. See how thick a sand and cement screed should be.
- Allow it to dry before laying a floor covering. We explain timing in how long sand and cement screed takes to dry.
- If the floor is only slightly uneven and thin, you may not need a screed at all. See self-levelling compound vs sand and cement screed.